Sandbank foundation installation

photosgallery: 

Bilfinger Marine & Offshore Systems has successfully finished the foundation installation for the € 1.2 billion offshore wind farm Sandbank.

The installation works started in summer 2015 and despite adverse weather conditions in November and December, the installation of the 72 Monopile and Transition Piece foundations was completed on 12th February within the projected schedule. (Photos: Bilfinger Marine & Offshore Systems)