Alstom implements DolWin3 offshore grid connection

Thursday, 7 March, 2013 - 15:15

The transmission grid operator responsible for the German North Sea, TenneT has awarded the offshore grid connection DolWin3 to Alstom. As the general contractor, Alstom will deliver and construct both the offshore and the onshore substation and connecting cable systems, together with their partners the platform builder Nordic Yards and the cable suppliers Prysmian. They will utilise DC technology as well as DC voltage source conversion technology (± 320 kV, 900 MW). The project has a total investment volume of more than € 1 billion. DolWin3 will be the third grid connection within the wind farm cluster DolWin in the southwestern North Sea, and will have a capacity of 900 MW. The project is scheduled to be completed in 2017.

The power generated at sea will be transferred to shore via an 83 km long high voltage direct current transmission line. The wind energy is then transported another 79 km from the coast to the substation Dörpen/West in Lower Saxony via a land cable. "Transmitting the electricity generated in wind farms to the grid on the mainland without energy loss is one of the main challenges of future supply infrastructure. With DolWin3 we are strengthening our position as a technology leader in the field of high voltage direct current transmission," says Grégoire Poux-Guillaume, President of the Power Transmission Division of Alstom.

Lex Hartman, a member of senior management at TenneT, says, "We are taking energy policy a step forward and helping to ensure that offshore wind energy can make a significant contribution to the energy supply of the future." DolWin3 is the eighth grid connection project with DC technology for TenneT. With three further AC technology projects, the transmission system operator will then bring a total of 6.2 GW of offshore wind energy on land. "Including DolWin3, we will invest more than € 7 billion in the energy turnaround," says Hartman.

Alstom has also secured a five-year service contract for the onshore and offshore substations, including the platform. The service package includes maintenance, spare parts supply and a technical support hotline.

Katharina Garus

Similar Entries

Schaeffler and ZF use jointly developed expert models to analyze and predict the condition of wind turbine gearboxes based on the actual loads that occur during operation

ZF Friedrichshafen and Schaeffler are collaborating to develop new solutions for predicting the operating life of wind turbine gearbox components based on the actual loads that occur during operation. Since September, the first wind turbine gearboxes equipped with sensors and condition monitoring systems have been supplying operating data to a cloud-to-cloud solution to enable this to happen.

Based on a thorough review of the latest project data, Westwood forecasts over 15,300 turbines to be installed over the 2018-2027 period with a total global cumulative capacity to reach just under 113 GW by 2027, inclusive of projects at the concept and speculative stages of development.

The heart of the Arkona offshore wind project in the German Baltic Sea has been completed on schedule. The electric offshore transformer station has now been successfully installed at a water depth of almost 30 meters. Moving the so-called "topside" from a barge onto the foundation with the crane ship Oleg Strasnov was the installation of the world's heaviest alternating current platform, which had previously been lifted in one block on the high seas.

Only one year after the successful commissioning of Taiwan’s pioneering Formosa 1 Phase 1 offshore wind power plant, Siemens Gamesa Renewable Energy (SGRE) has been contracted to supply an additional 120 MW of capacity for Formosa 1 Phase 2. The contracts signed today are subject to the joint venture’s final investment decision and financial close, which are expected later this year. In addition to the turbine supply agreement, a 15-year Full service agreement is also signed and includes the provision of spare parts and tools to help ensure the reliability and optimal performance of the turbines. The installation of the 20 SWT-6.0-154 wind turbines will start in 2019. They will expand the total capacity of Formosa 1 wind power plant to 128 MW.

 
 

Contact