Arkona offshore project still on course

Monday, 9 April, 2018 - 10:30

The heart of the Arkona offshore wind project in the German Baltic Sea has been completed on schedule. The electric offshore transformer station has now been successfully installed at a water depth of almost 30 meters. Moving the so-called "topside" from a barge onto the foundation with the crane ship Oleg Strasnov was the installation of the world's heaviest alternating current platform, which had previously been lifted in one block on the high seas.

The largest single component of the billion-euro project weighs more than 5,000 tons and consists of the jacket foundation anchored in the seabed and the topside with the electrical switchgear and transformers. It is the size of an eight-storey apartment building and has a helipad at an altitude of 70 metres above sea level. The construction of the transformer station at the French shipyard STX required more than 500,000 working hours.

The joint venture consisting of E.ON and Statoil will jointly use the platform with the transmission grid operator 50Hertz. The unmanned station is located in the middle of the construction site of the wind farm and will bundle the electricity produced by the 60 wind turbines, which is then transported to the mainland by sea cable. The substation is operated from the operating station of the wind farm in the port of Mukran Port in Sassnitz on Rugen island, while E.ONs Offshore Marine Coordination Center in Hamburg monitors and controls the operation.

The next step in the construction phase will be the laying of the internal parking cabling. Finally, in late summer, the erection of the wind turbines on the foundations already installed will start. The complete commissioning of the entire wind farm is planned for 2019.

The Arkona project is located 35 kilometres northeast of the island of Rugen. The wind farm will have an output of 385 megawatts (MW) and can theoretically supply around 400,000 households with renewable energy. The investment volume amounts to 1.2 billion euros. Compared to conventionally generated electricity, Arkona saves up to 1.2 million tons of CO2 per year. 60 turbines in the six-megawatt class from Siemens will be installed. The plants are based on monopile foundations in water depths of 23 to 37 metres.

Source: E.ON

Similar Entries

Receiving the award in Hamburg: E.ON Project director Holger Matthiesen with Andrea Thilo, moderator of the ceremony.  (Photo: E:ON)

The newly developed corrosion protection at offshore wind project Arkona in the German Baltic Sea received the German Renewables Award in Hamburg.

Vroon Offshore Services and Ampelmann have joined forces to deploy a Walk to Work (W2W) solution for the Arkona offshore wind farm, located in the German Baltic Sea. Vroon’s VOS Stone vessel, the newest addition to its offshore-support fleet, will be mobilised with an Ampelmann A400 gangway system. The gangway, launched in 2017, will be utilised for the first time for W2W operations during array cabling work and commissioning of the Arkona offshore wind farm.

Siemens Gamesa will supply the new 8 MW direct-drive offshore turbine to a 500 MW project in France (photo: Siemens Gamesa)

Siemens Gamesa Renewable Energy will supply 62 units of its new 8 MW offshore wind turbine, the SG 8.0-167 DD, to the 500 MW Saint Brieuc project off the coasts of Brittany. The ordered direct drive wind turbine will replace Adwen’s AD 8-180 model after Siemens Gamesa has decided to focus on offshore direct drive platform.

In 2017, Mammoet, heavy lifting and transport specialist, has been contracted by Lamprell Energy for the heavy lifting and transport of 60 jacket foundations for the East Anglia One offshore wind farm project.

 
 
 

Contact