First foundation for Nordsee One successfully installed

Wednesday, 16 December, 2015 - 12:15
The installation vessel Innovation carries foundation pieces out to sea. (Photo: RWE Innogy)
The installation vessel Innovation carries foundation pieces out to sea. (Photo: RWE Innogy)

The first monopile for the 332 MW Nordsee One offshore wind project was successfully installed ahead of schedule on December 15, 2015. Installation will continue through the remainder of 2015 and into 2016.

The Nordsee One offshore wind farm, located in German territorial waters in the North Sea, will consist of 54 Senvion turbines and is owned by Northland Power Inc. (85 %) and RWE Innogy GmbH (15 %). Nordsee One has contracted installation of the monopiles from GeoSea. The monopiles were produced by Ambau. They are being installed in water depths ranging between 25 and 29 m.

“Today’s accomplishment is very exciting for everyone involved,” said Pierre Lestienne, Managing Director of the project. “Achieving this milestone reflects months of effort and progress, and was a result of the hard work and cooperation of our team and project partners.” John Brace, CEO of Northland, adds: “Thanks to the skill and effort of our project team, we reached this important milestone ahead of time and on budget.”

Katharina Garus / RWE Innogy

Similar Entries

A hat-trick of offshore wind industry firsts has been achieved within a fortnight in North-east Scotland after the world’s most powerful single turbine was successfully installed on April 9th for Vattenfall’s European Offshore Wind Deployment Centre (EOWDC). The turbine is the first of 11 to be deployed at the facility in Aberdeen Bay. Two turbines will have a capacity of 8.8 MW, the other nine will have a capacity of 8.4 MW

Nordsee One offshore wind farm is expected to produce an annual output of more than 1,300 GWh of green energy. (Photo: Innogy SE)

332 MW Nordsee One offshore wind farm, located approximately 40 km north of the island of Juist, achieved full completion. The project was fully commissioned on schedule and below its total budget of €1.2 billion.

The 25,000 tonne Asian Hercules III installs the first suction bucket jacket foundation for the EOWDC, off Aberdeen Bay. (Photo: Vattenfall)

North-east Scotland has marked a UK offshore wind first following the successful installation of the first pioneering suction bucket jacket foundation for Vattenfall’s 11-turbine European Offshore Wind Deployment Centre (EOWDC) in just 15 hours. The EOWDC in Aberdeen Bay is the first offshore wind project to deploy the foundations at commercial scale with each of the 11 steel jacket foundations weighing in at almost ten Boeing 747s.

In 2017, Mammoet, heavy lifting and transport specialist, has been contracted by Lamprell Energy for the heavy lifting and transport of 60 jacket foundations for the East Anglia One offshore wind farm project.

 
 
 

Contact