First turbine successfully installed at Nordsee One

Thursday, 9 March, 2017 - 12:30
Installation of first Senvion turbine at Nordsee One was completed according to schedule. (Photo: innogy SE)
Installation of first Senvion turbine at Nordsee One was completed according to schedule. (Photo: innogy SE)

Installation of the 54 Senvion 6 MW wind turbines that will comprise the Nordsee One Offshore Wind Farm has commenced at the base port in Eemshaven.

Two sets of wind turbines each consisting of a fully assembly steel tower, a nacelle and a pre-assembled rotor, were loaded onto the installation vessel MPI Enterprise, which transported the components to the construction site at sea located approximately 40 km north off the island of Juist. Upon arrival at the offshore site, the first of the two turbines was installed using the installation vessel’s own crane.

The nacelles alone weigh-in at approx. 335 tonnes, the tower itself measures almost 70 metres overall in length, and weighs over 240 tonnes. Each rotor blade is 61 meters in length and weighs approximately 20 tonnes.

In April 2016 installation of the turbine foundations was completed. The substation was installed last summer, and the inter-array cable laying was successfully completed in September 2016. Once completed, the Nordsee One wind farm will consist of 54 wind turbines of the type Senvion 6.2M126 with an overall installed capacity of 332 MW. Commissioning of the wind farm is anticipated by the end of 2017. Nordsee One is owned by Northland Power Inc. (85%) and innogy SE (15%).

Pierre Lestienne, Managing Director (CFO) of Nordsee One GmbH explained: “We have reached this important milestone according to schedule and within budget. I'm really proud of this achievement. This outcome is the result of precise planning and efficient execution.”

Tim Kittelhake, Managing Director (COO) of Nordsee One GmbH added: “The team worked together hand-in-hand, so the loading of the first major components at our base port in Eemshaven, as well as the installation at sea, both went very smoothly. We look forward to installation of the next turbines, which will follow immediately. We plan to have all turbines installed and commissioned by the end of this year.”

Northland Power / innogy SE /
Nordsee One / Silke Funke

Similar Entries

The first turbine on DONG Energy’s offshore wind farm Burbo Bank Extension has been installed. It was also the first installation ever of the new 8 MW turbine produced by MHI Vestas, the V164-8.0 MW.

The first wind energy plant of the offshore wind farm Nordergründe has been installed. (Photo: wpd)

On August 16, the first wind energy turbine has been installed at the offshore wind site Nordergründe in the German North Sea. The first turbine of the 111 MW wind park was produced by Senvion and has a capacity of 6.15 MW.

The 59 inter-array cables for offshore wind farm Nordsee One have been installed successfully with the help of the vessels Siem Aimery (shown on the left) and Siem Moxie (on the right). (Photo: SIEM Offshore Contractors GmbH)

Three weeks ahead of schedule, the inter-array cables for offshore wind farm Nordsee One have been installed by SIEM Offshore Contractors GmbH. The foundations and the offshore substation for the 54 wind turbines have also already been installed.

VBMS recently repaired two inter-array cables and one export cable in UK waters. With its cable-laying vessels being deployed for cabling projects at Galloper, Rampion and Walney Extension offshore wind farms, VBMS used Stemat 82 to carry out these cable repairs. The cable-laying barge’s 8-point mooring system and 2.3 depth made it highly suitable for repairing two inter-array cables in the shallow waters of the outer Thames Estuary. The export cable repair was carried out 20 kilometers offshore, in the Irish Sea.