Mammoet successfully loads out the first batch of jackets for East Anglia ONE offshore wind farm project

Wednesday, 11 April, 2018 - 16:00

In 2017, Mammoet, heavy lifting and transport specialist, has been contracted by Lamprell Energy for the heavy lifting and transport of 60 jacket foundations for the East Anglia One offshore wind farm project.

ScottishPower Renewables’ new £2.5 billion offshore wind farm, East Anglia One, will consist of 102 turbines in the North Sea, each rated at 7 megawatts, totaling an overall generating capacity of 714 megawatts. It is expected to generate power for more than 500,000 British homes every year. Lamprell was awarded the fabrication and supply of 60 jacket foundations and their accompanying piles.

The jackets are placed on the seabed and form a secure platform for wind turbine generators to be fixed to. Under the contract, Mammoet has to perform heavy lifting and upending, weighing, transport and load-out of the jackets at Lamprell’s Jebel Ali, Hamriyah and Sharjah yards in the United Arab Emirates. Once complete, the jackets will be loaded onto a specialist ship bound for Europe.

Michel Bunnik, Mammoet’s Regional Sales Director said: “Mammoet are proud to be the partner of choice for the heavy lift and transport services for Lamprell and excited to have the opportunity to contribute to a project of such a significance”.

Source: Mammoet

Similar Entries

The last three monopiles are loaded onto the barge in Rostock (pict.: EEW SPC/Van Oord)

On the evening of 19 December, 2018, EEW Special Pipe Constructions GmbH loaded the last three monopiles for the German offshore wind project Deutsche Bucht in the Rostock port.

The Heavy Lift Jack-Up Vessel Innovation lifted the Topside on the foundation (source: EnBW)

The Topside of the Offshore substation of the wind farm EnBW Albatros was installed the night from March 26 to 27, 2019. The Heavy Lift Jack-Up Vessel (HLJV) Pacific Ospray had loaded the Topside in Rotterdam.

Schaeffler and ZF use jointly developed expert models to analyze and predict the condition of wind turbine gearboxes based on the actual loads that occur during operation

ZF Friedrichshafen and Schaeffler are collaborating to develop new solutions for predicting the operating life of wind turbine gearbox components based on the actual loads that occur during operation. Since September, the first wind turbine gearboxes equipped with sensors and condition monitoring systems have been supplying operating data to a cloud-to-cloud solution to enable this to happen.

Boarding Den Helder Airport (pict: PressOffshore PR & Content)

Den Helder Airport (DHA) will facilitate helicopter flights for the maintenance of the Deutsche Bucht offshore wind farm for Vestas in the coming years. At the same time, offshore wind farm constructor Van Oord has finalized a call-off contract for the same German wind farm.

 
 

Contact