Nordic Yards has undocked the offshore platform BorWin beta

Thursday, 8 August, 2013 - 10:15

The legs of the offshore platform BorWin beta, which are currently pointing upwards, will later be attached to the foundation and the platform will rise 20 m above the water level. (Photo: Nordic Yards)

Nordic Yards has undocked the transformer platform BorWin beta. The offshore platform will now convert electricity from wind farms in the German North Sea to direct current and route it to the mainland. A few finishing tasks will be completed by the end of August, then the platform will be pulled by tug boats to its installation location 125 km off the German coast.

The topside, currently located at the quay in Warnemünde, will be installed on a foundation that has already been prepared for it in the North Sea. The legs of the platform, which are currently pointing upwards, will be guided into the foundation and secured. Subsequently, the entire platform will rise out of the water on its own legs and will then stand 20 m above the water level. A station for high-voltage direct current (HVDC) that can handle up to 800 MW is installed on the platform.

When BorWin beta is undocked, SylWin alpha will be visible, which is the third platform under construction at Nordic Yards. The topside alone is the size of an 11-story building and is being assembled on a special substructure in the dock. Construction of the fourth transformer platform, DolWin gamma, will begin next year.

Katharina Garus

Similar Entries

The SylWin1 platform (864 MW), which measures 83 x 56 x 26 m (L x W x H), is the world's largest installed converter platform. It will transmit the energy produced by the three North Sea wind farms Dan Tysk, Butendiek and Sandbar ashore.

The SylWin1 platform (864 MW), which measures 83 x 56 x 26 m (L x W x H), is the world's largest installed converter platform. It will transmit the energy produced by the three North Sea wind farms Dan Tysk, Butendiek and Sandbar ashore. (Photo: TenneT)

Just a few days ago, Siemens had announced that the HVDC converter platform HelWin beta has been completed. Its next offshore platform in the North Sea is now also ready. SylWin alpha is the largest HVDC platform that has ever been installed in the North Sea.

3,200 tonnes floating over the North Sea: The offshore transformer station hangs from the hook of the Oleg Strashnov. (Photo: Vattenfall)

The most difficult crane lift in the German offshore wind project DanTysk is complete: On 1 August, the 3,200 tonne substation was positioned on its jacket substructure.

The new DBB jack-up vessel will be able to work in water depths of up to 45 m

The new DBB jack-up vessel will be able to work in water depths of up to 45 m. (Graphic: DBB)

At Nordic Yards,a 390-tonne section of a new wind turbine jack-up vessel was laid down in the Wismar dock on September 16, marking a further milestone in the construction of the 80 m long and

As OWI previously reported, there have been several technical malfunctions over the course of the last few months at the offshore grid connection BorWin alpha. However, the joint search for the cause of the problems by the transmission system operator TenneT, the contractor for the grid connection ABB and the operator of the connected wind farm Bard Offshore 1 has also suffered setbacks.