Nordic Yards has undocked the offshore platform BorWin beta

Thursday, 8 August, 2013 - 10:15
Photo: Nordic Yards

Nordic Yards has undocked the transformer platform BorWin beta. The offshore platform will now convert electricity from wind farms in the German North Sea to direct current and route it to the mainland. A few finishing tasks will be completed by the end of August, then the platform will be pulled by tug boats to its installation location 125 km off the German coast.

The topside, currently located at the quay in Warnemünde, will be installed on a foundation that has already been prepared for it in the North Sea. The legs of the platform, which are currently pointing upwards, will be guided into the foundation and secured. Subsequently, the entire platform will rise out of the water on its own legs and will then stand 20 m above the water level. A station for high-voltage direct current (HVDC) that can handle up to 800 MW is installed on the platform.

When BorWin beta is undocked, SylWin alpha will be visible, which is the third platform under construction at Nordic Yards. The topside alone is the size of an 11-story building and is being assembled on a special substructure in the dock. Construction of the fourth transformer platform, DolWin gamma, will begin next year.

Katharina Garus

Similar Entries

Prysmian produced the cables for the Borwin2 HVDC submarine cable connection with a transmission capacity up to 800 MW. (Photo: Prysmian Group)

Prysmian Group, specialist in energy and telecom cable systems industry, announces that the interconnection between the Veja Mate offshore wind farm and the offshore grid connection system Borwin2 in the German North Sea has been plugged in.

wpd completed installation of the transformer platform for the nearshore-project Nordergründe. (Photo: wpd)

Under the project leadership of the Bremen-based project developer wpd, the OWP Nordergründe GmbH & Co. KG completed installation of the transformer platform for the nearshore-project Nordergründe.

Now installed, the converter sits 66 feet above the waves. (Photo: TenneT)

TenneT and GE have successfully installed the DolWin3 offshore converter station in the south-western German North Sea, approximately 80 kilometers from land.

Full-scope-project EnBW Albatros: Siemens Gamesa supplies 16 direct-drive SWT-7.0-154 wind turbines on monopile foundations and the grid connection via a Siemens Offshore Transformer Module. (Photo: Siemens Gamesa)

Following the 497 MW order for the EnBW Hohe See offshore wind farm, EnBW has also awarded Siemens Gamesa Renewable Energy with the installation of the neighbouring 112 MW project EnBW Albatros.