Offshore wind project Rampion starts power generation

Tuesday, 28 November, 2017 - 11:30
The first of 116 MHI Vestas 3.45MW tubines has been commissioned at Rampion offshore wind farm. (Graphic: E.ON)
The first of 116 MHI Vestas 3.45MW tubines has been commissioned at Rampion offshore wind farm. (Graphic: E.ON)

The offshore wind farm Rampion in the English Channel has started generating electricity. According to E.ON, the first turbine was commissioned. 115 additional turbines will be connected to the grid in stages over the next few months.

The offshore work for the Rampion project began in autumn 2015 with the preparation of the seabed for the turbine foundations. The first monopile was installed at the beginning of 2016. The installation of the turbines began in March 2017 and was completed ahead of schedule in September.

The 400 megawatt Rampion project is located 13 kilometres off the Sussex coast. Owners are E.ON, the British Green Investment Rampion Ltd. and the Canadian energy company Enbridge. The project is being built and operated by E.ON as majority owner.

E.ON / Silke Funke

Similar Entries

The 151-metre, self-propelled, DP2 jack-up rig Seafox 5 has left the Damen Verolme Rotterdam (DVR) shipyard following a four-month refit in which the boom of its main crane was lengthened to prepare it for a new contract, along with a range of maintenance and other upgrade works. Seafox 5 is now equipped to undertake offshore wind projects involving the next generation of larger wind turbines in water depths of up to 65 metres.

In 2017, Mammoet, heavy lifting and transport specialist, has been contracted by Lamprell Energy for the heavy lifting and transport of 60 jacket foundations for the East Anglia One offshore wind farm project.

The heart of the Arkona offshore wind project in the German Baltic Sea has been completed on schedule. The electric offshore transformer station has now been successfully installed at a water depth of almost 30 meters. Moving the so-called "topside" from a barge onto the foundation with the crane ship Oleg Strasnov was the installation of the world's heaviest alternating current platform, which had previously been lifted in one block on the high seas.

Only one year after the successful commissioning of Taiwan’s pioneering Formosa 1 Phase 1 offshore wind power plant, Siemens Gamesa Renewable Energy (SGRE) has been contracted to supply an additional 120 MW of capacity for Formosa 1 Phase 2. The contracts signed today are subject to the joint venture’s final investment decision and financial close, which are expected later this year. In addition to the turbine supply agreement, a 15-year Full service agreement is also signed and includes the provision of spare parts and tools to help ensure the reliability and optimal performance of the turbines. The installation of the 20 SWT-6.0-154 wind turbines will start in 2019. They will expand the total capacity of Formosa 1 wind power plant to 128 MW.