Project certification for Sandbank offshore wind farm completed

Wednesday, 31 May, 2017 - 11:45
TÜV SÜD presented the project certificate for the Sandbank offshore wind farm off the coast of Sylt in the North Sea. (Photo: Vattenfall)
TÜV SÜD presented the project certificate for the Sandbank offshore wind farm off the coast of Sylt in the North Sea. (Photo: Vattenfall)

TÜV SÜD’s experts have supported the large-scale project over the past 30 months. Certification was awarded in accordance with the standard of the German Maritime and Hydrographic Agency (BSH), and covers supervision and inspection of wind turbine, foundation, sub-station and internal cable manufacturing, transport, installation and commissioning for the wind farm.

The Sandbank offshore wind farm is around 90 kilometres to the west of the island of Sylt, in the North Sea. After DanTysk, it is the second large-scale infrastructure project to have been realised by the project partners under Vattenfall’s management. Work on the Sandbank wind farm began in July 2015. The last of the total of 72 wind turbines was put into operation at the end of January. The wind farm’s entire power output of 288 MW is fed into the German grid.

“The Sandbank project is three months ahead of schedule, not least thanks to the smooth collaboration with TÜV SÜD”, says Philipp Degenhardt, Sandbank’s Team Lead - Project Certification and Interface Management.

“This successful certification is confirmation that the Sandbank wind farm complies with national standards and that the safety of the turbines is guaranteed”, explains Malte Lossin from TÜV SÜD Industrie Service GmbH, the responsible Project Manager.

TÜV SÜD / Silke Funke

Similar Entries

With the installation of the last of a total of 72 turbines at Sandbank Offshore Wind Farm the construction phase has been completed three months ahead of the originally planned time schedule. (Photo: Vattenfall)

The offshore wind power plant Sandbank, located 90 kilometres west of the island of Sylt, is now fully installed and commissioned. On 21 January the installation vessel MPI Adventure together with Siemens erected the last turbine. Four days after that the last turbine “SB41” has achieved ‘final commissioning’ already

Length 88 m, beam 18 m, speed 13.5 knots: The SOV Windea Leibniz from Ulstein Verft will work at the Sandbank wind farm. (Photo: Ulstein Group / Eide Studio)

The Windea Leibniz wind farm service vessel was delivered on-time from Ulstein Verft to Bernhard Schulte Offshore and ICBC Leasing and named at a ceremony in Ulsteinvik. The vessel will shortly commence service at the Sandbank offshore wind farm for Siemens.

The installation of the foundations for offshore wind farm Sandbank. (Photo: Vattenfall / Ulrich Wirrwa)

The offshore wind farm Sandbank has supplied its first wind power to the German electricity network. The first of the wind farm’s 72 wind turbines are successively being commissioned for power production.

International marine and engineering consultancy LOC Renewables is carrying out marine warranty surveying (MWS) services on what will be the world’s biggest wind farm, DONG Energy’s Hornsea Project One. The site, which will consist of 174 turbines installed off the Yorkshire coast in the North Sea and deliver power to more than one million homes, is scheduled for commissioning in 2020.