Riffgat: Inauguration without grid connection

Wednesday, 14 August, 2013 - 11:00
Photo: EWE

EWE AG from Oldenburg, Germany, celebrated the completion of the offshore wind farm Riffgat on 10 August. Riffgat is Germany's first commercial North Sea wind farm. However, it is not producing electricity yet because the wind turbines are ready but the grid connection is not.

The utility company EWE installed a total of 30 wind turbines in only 14 months of construction for Riffgat off the coast of Borkum. However, the grid connection was not finished in time. Some 15 km of cable are missing, which the grid operator TenneT is expected to be able to lay in February 2014. According to TenneT, the cable laying operation is being delayed because there have been unforeseen problems during the recovery of old munitions from the seabed. "We are very disappointed by this delay - in our opinion, it could have been avoided," said Werner Brinker, Chairman of the Board of EWE AG.

It is detrimental for wind turbines at sea not to be in operation, so EWE temporarily equipped the turbines with diesel generators. This allows the mechanical components to be in motion so that they do not get rusty in the aggressive sea air. Instead of generating electricity, the wind turbines and the substation are consuming electricity for cooling as well. The generators are burning through 22,000 L of diesel every month, according to energy supplier EWE from Oldenburg.

Construction was literally a big task: Each of the 30 wind turbines has a capacity of 3.6 MW and a rotor diameter of 120 m. The hub height is 90 m, which corresponds to the height of the Bremen Cathedral; the overall height of the turbines is 150 meters from the water surface to the upper rotor blade tip. The colossal SWT-3.6-120 turbines from Siemens were transported from Denmark to their destination and anchored in 18 to 23 m water depth, and new sound protection measures were used to protect marine mammals.

Katharina Garus

Related articles:

Foundations for Riffgat offshore wind farm in place
Mitsubishi pledges support to TenneT
Siemens' fire detection and extinguishing system is certified

Similar Entries

Schaeffler and ZF use jointly developed expert models to analyze and predict the condition of wind turbine gearboxes based on the actual loads that occur during operation

ZF Friedrichshafen and Schaeffler are collaborating to develop new solutions for predicting the operating life of wind turbine gearbox components based on the actual loads that occur during operation. Since September, the first wind turbine gearboxes equipped with sensors and condition monitoring systems have been supplying operating data to a cloud-to-cloud solution to enable this to happen.

The two purpose-built vessels, each with a length of approximately 140m, are also operated by deugro Danmark A/S exclusively for Siemens Gamesa. (Photo: SGRE)

Siemens Gamesa has been able to transfer its new logistics concept, announced in 2015 into reality. By using a Ro/Ro solution the company expects to save about 20 % in costs and increase safety at the same time.

Prysmian Group announces an investment in excess of €170 million in a new cutting-edge cable laying vessel. This strategic asset is meant to bolster Prysmian’s turnkey approach, under which it delivers end-to-end EPCI projects.

The heart of the Arkona offshore wind project in the German Baltic Sea has been completed on schedule. The electric offshore transformer station has now been successfully installed at a water depth of almost 30 meters. Moving the so-called "topside" from a barge onto the foundation with the crane ship Oleg Strasnov was the installation of the world's heaviest alternating current platform, which had previously been lifted in one block on the high seas.

 
 

Contact