Successful installation of transformer platform for Nordergründe

Friday, 22 September, 2017 - 12:15
wpd completed installation of the transformer platform for the nearshore-project Nordergründe. (Photo: wpd)
wpd completed installation of the transformer platform for the nearshore-project Nordergründe. (Photo: wpd)

Under the project leadership of the Bremen-based project developer wpd, the OWP Nordergründe GmbH & Co. KG completed installation of the transformer platform for the nearshore-project Nordergründe.

The more than 2,000 tons transformer platform is now sitting on a monopile foundation at the wind farm which is situated at 15 km to the North-East of the island of Wangerooge, bringing the completion of the 111 MW wind farm within reach.

Commissioning of the project had originally been planned for the end of the year 2016, but was set back by the insolvency proceedings of the transformer platform manufacturer, BVT Bremen GmbH & Co. KG, in the fall of 2016. After analyzing different possibilities, banks and equity providers decided to finish the construction of the transformer platform under wpd’s leadership on their own.

“We were able to fully implement the plan for further construction of the transformer platform, which was decided in November of 2016, and we were able to install the transformer platform almost to the day,” said Achim Berge Olsen, Managing Director of OWP Nordergründe GmbH & Co. KG and of wpd offshore GmbH. “I’m happy to say that we have advanced the project by a giant step and that we are now able to prepare for final commissioning.”

Besides construction of the transformer platform, wpd has also been responsible for the installation of the 18 turbines of the Senvion 6.2M126 type and will further on operate the wind farm. The Nordergründe wind farm is situated in water depths of 10 meters within the 12 sea mile zone of the German North Sea. Grid connection is via individual connection by the grid operator Tennet.

All the component manufacturers are from the German north-western region. Besides of Senvion (wind turbine generators), these are the companies Ambau (foundations), NSW (internal wind farm cabling) and Bilfinger Marine & Offshore Systems, now Van Oord (installation).

Financial close of the projects had been completed in June of 2015 with the participation of European Investment Bank and KfW IPEX. Besides wpd, John Laing Group plc and Gothaer Insurance Group are acting as equity providers.

wpd / Silke Funke

Similar Entries

The heart of the Arkona offshore wind project in the German Baltic Sea has been completed on schedule. The electric offshore transformer station has now been successfully installed at a water depth of almost 30 meters. Moving the so-called "topside" from a barge onto the foundation with the crane ship Oleg Strasnov was the installation of the world's heaviest alternating current platform, which had previously been lifted in one block on the high seas.

International engineering and operations support services contractor ODE, an integral part of the DORIS Group, has been awarded a consultancy framework agreement by ScottishPower Renewables for the provision of client representatives during construction activities for the East Anglia ONE Offshore Windfarm. The agreement is the latest development in a ten-year relationship between ODE and ScottishPower Renewables, which plans to invest £2.5 billion in the East Anglia ONE project.

Only 7 days were needed for A1 Offshore Solutions ApS and SMST between contract signing and mobilization of the SMST motion compensated gangway on board the Eurus Express. The Platform Supply Vessel (PSV) is now equipped to safely transfer technicians from vessel to transition piece in the Hornsea Project One offshore wind farm. A great effort by all parties involved.

The 25,000 tonne Asian Hercules III installs the first suction bucket jacket foundation for the EOWDC, off Aberdeen Bay. (Photo: Vattenfall)

North-east Scotland has marked a UK offshore wind first following the successful installation of the first pioneering suction bucket jacket foundation for Vattenfall’s 11-turbine European Offshore Wind Deployment Centre (EOWDC) in just 15 hours. The EOWDC in Aberdeen Bay is the first offshore wind project to deploy the foundations at commercial scale with each of the 11 steel jacket foundations weighing in at almost ten Boeing 747s.

 
 

Contact