Sandbank Offshore Wind Farm fully commissioned

Thursday, 26 January, 2017 - 12:15
With the installation of the last of a total of 72 turbines at Sandbank Offshore Wind Farm the construction phase has been completed three months ahead of the originally planned time schedule. (Photo: Vattenfall)
With the installation of the last of a total of of 72 turbines at Sandbank Offshore Wind Farm the construction phase has been completed three months ahead of the originally planned time schedule. (Photo: Vattenfall)

The offshore wind power plant Sandbank, located 90 kilometres west of the island of Sylt, is now fully installed and commissioned. On 21 January the installation vessel MPI Adventure together with Siemens erected the last turbine. Four days after that the last turbine “SB41” has achieved ‘final commissioning’ already

A total of 72 Siemens SWT-4.0 130 wind turbines in the 4 MW class were installed, providing a total capacity of 288 MW. Sandbank is the second joint offshore wind project for Vattenfall and SWM already. Together with the sister-project DanTysk (in full operation since early 2015) both wind power plants will provide a combined portfolio of 576 MW of installed generation capacity.

The investment costs for the Sandbank offshore wind farm are around € 1.2 billion. Vattenfall holds a 51% stake in Sandbank Offshore GmbH, which was set up to implement the project, while Stadwerke München (SWM) holds a 49% stake.

Now that the wind farm is in full operation, an offshore substation collects the wind energy of all 72 turbines, transform it from an AC voltage of 33 kilovolts (kV) to 155 kV, and deliver it to a converter station, from where the energy is transported as DC over a distance of 165 kilometres to the landing point in Büsum, Schleswig-Holstein. The first Sandbank wind turbine was installed end of July 2016.

During the commissioning phase of the wind turbines a modified type of vessel including a “walk-to-work” gangway was deployed by the project for the first time in the German North Sea. This system equalizes the wave motions of the North Sea and features a special gangway that enables the commissioning teams to step over to the wind turbines directly, with sea conditions of up to 2.5 metres in height. The new concept also enables for work with enhanced safety standards and to be carried out 24 hours per day.

“We are very pleased that the installation of the wind turbines for Sandbank was running so successfully”, said Martin Zappe, technical Head of the project at Vattenfall. “The technology deployed on the project as well as the co-operation between all involved parties have gained a lot in terms of maturity. Projects of this size are now much more standardized and efficient. We will use these experiences for future projects to implement them as cost efficient as possible, also with regards to the new auction system for coming offshore projects in Germany.”

Christian Vogt, Head of Corporate Investment Management at Stadtwerke München commented: “Offshore wind power plays a key role to meet SWM’s ambitious targets for the expansion of renewable energy. By 2025, SWM is aiming to produce as much green electricity as required to power the entire city of Munich. Sandbank is SWM’s fourth offshore project, which is implemented successfully and even faster than originally scheduled. I would like to thank all those who contribute with their commitment to the success of this very complex project."

Silke Funke / Vattenfall

Similar Entries

Nordsee One offshore wind farm is expected to produce an annual output of more than 1,300 GWh of green energy. (Photo: Innogy SE)

332 MW Nordsee One offshore wind farm, located approximately 40 km north of the island of Juist, achieved full completion. The project was fully commissioned on schedule and below its total budget of €1.2 billion.

Ampelmann, the global leader in offshore access solutions, has created, in cooperation with Seaway Heavy Lifting, an industry first innovation allowing workers safe and efficient access to install the jackets for 84 wind turbines on the Beatrice Offshore Windfarm Limited project in the Outer Moray Firth.

The Board of The Renewables Infrastructure Group Limited is pleased to announce that the Company has completed an investment to acquire a 14.7% indirect equity interest in the Sheringham Shoal Offshore Wind Farm, a 316.8MW project located in the North Sea off the coast of Norfolk.

The topside for the offshore substation for the Merkur Offshore Wind Farm has been installed over the weekend. This piece of technology is the result of a close cooperation between Belgian companies that are major players in the international offshore wind energy market. With companies like Tractebel (engineering), ENGIE-Fabricom (electromechanics), Iemants (steel constructions) and GeoSea (contracting) Flanders had developed a leading cluster of offshore wind energy experts, executing the most complex projects on the European market.

 
 
 

Contact