Vibration instead of ramming

Wednesday, 3 September, 2014 - 10:30
A new hope may be hanging from the hook of this crane. The new vibratory ram for installing monopiles is currently being tested in a sandpit near Cuxhaven.
A new hope may be hanging from the hook of this crane. The new vibratory ram for installing monopiles is currently being tested in a sandpit near Cuxhaven.
(Photo: Torsten Thomas)

The offshore wind industry is pinning big hopes on a new vibration process. It is designed to drive piles into the ­seabed faster, cheaper, and more carefully. ­Practical testing has been promising.

For a long time, nothing happens. Then the earth shakes, the pile vibrates and sinks one large section at a time into the ground of a gravel pit. In no time, the 21 m-long pile is already at the desired depth. There are thumbs-up all around as satisfied ­engineers pat each other on the back. The ­process tested in this ­gravel pit near ­Cuxhaven in the northern ­German lowlands will soon become an everyday event at sea. “At least in comparable sediments,” says Tobias Griesshaber. Griesshaber, a project lead at RWE Innogy, explains: “The conditions here are identical to those in much of the North Sea, and we’ve never been so close to reality. That’s what makes the project unique in the world.”

The energy provider, together with E.ON, Dong Energy, ­Vattenfall and EnBW shelled out a good ¤ 6 million to glean these new insights. The British organisation ­Carbon Trust contributed a further 33 % of the project costs. The sandpit near Cuxhaven is the ideal ­testing ground because in prehistoric times it was covered by the North Sea at high tide. A total of three tube-piles will be driven into the former seabed using the vibration technique and another three using a 1,200 t pile driver made by IHC Merwede. Sensitive measuring instruments monitored the work. Then the project participants will have a break of a few weeks before the decisive phase begins in August.

During that phase, a rammed tube and a vibrated tube will be tensioned against each other with a force of 20 MN. This force measure­ment is intended to provide insight into, “whether vibrated tubes have the same stability as the rammed ­variety. The emphasis will be on monopiles, which are still the preferred foundation type,” says Griesshaber. That is why the test piles, with their diameter of 4.3 m and length of 21 m, roughly correspond to the piles that will later have to stand up reliably in the seabed.

For the sake of safety, authorities and certification bodies have so far required that piles have to be driven into the seabed to a depth of at least eight times their diameter. With its powerful vibration, a vibrating ram liquefies the soil, thereby driving the pile into the seabed. These are precisely the differences that are set to be examined through the testing regime.

Easy on material and fast

If the tests go well, they would be a big step in the right direction because every strike with the ram puts a load on the steel and ultimately takes a toll on more than just its service life. Because the vibrating ram works faster ­– and ­particularly because it is so much quieter – the participants in the project are ­convinced that the environmental noise pollution regulations that apply in some countries will be easy to adhere to, and very likely will be far below the permissible noise ­thres­holds. Both of these benefits are expected to result in significant cost savings because they will eliminate the need for noise reduction measures, such as bubble curtains or noise insulating enclosures. “That, along with the prospect of only having to work with a single machine under the right soil conditions, is the driving force behind the project,” says Griesshaber.

Concrete hopes are resting on a vibratory hammer made by PVE ­Piling & Drilling Rigs BV. Especially for the project, the Dutch company has designed a hydraulic power package with twelve vibrating elements. With a static moment of 500 kg the machine is currently one of the largest devices on the market and develops the equivalent of 1,000 t of energy. In the test series, a crane first places the vibro hammer into the tube. The ram is held in place on the pile by four cheeks which develop 300 t of pressure each.

The ram itself is a real lightweight by comparison at just 60 t – a comparable hammer weighs some 245 t. Because these are still needed for other types of sediments, IHC Cuxhaven is trying a new ­process for the first time ever. The piles are ­driven at a higher frequency with lower energy. While that ulti­mately means more strikes to the pile, it creates less noise. During testing the noise was measured at 145 dB, which is far below the 160 dB ­allowed within a 750 m radius of pile driving in the North Sea. Sea creatures, if they could, would ­welcome the tests in the gravel pit.

Torsten Thomas
 

Similar Entries

Based on a thorough review of the latest project data, Westwood forecasts over 15,300 turbines to be installed over the 2018-2027 period with a total global cumulative capacity to reach just under 113 GW by 2027, inclusive of projects at the concept and speculative stages of development.

As of April 30, Boskalis presents its integrated service portfolio for the offshore energy market under one single brand name. As a result, Dockwise, Fairmount and VBMS, subsidiaries of Royal Boskalis Westminster N.V., will continue to offer their services under the brand name Boskalis.

Siemens Gamesa Renewable Energy (SGRE) took a new step in reinforcing its offshore strategy in China today when signing an additional licensing agreement with partner Shanghai Electric. This agreement is in line with the information on licensing as presented at the SGRE Capital Markets Day on February 15, 2018, and a part of SGRE’s L3AD2020 strategy.

Siemens Gamesa Renewable Energy released its results for the second quarter of fiscal year 2018 (January-March) today. Commercial activity in the second quarter of 2018 remained strong: after three consecutive quarters of growth in order intake, the order backlog has reached €22,041 million and is back to market-peak levels of March 2017.

 
 

Contact