Arkona offshore project still on course

Monday, 9 April, 2018 - 10:30

The heart of the Arkona offshore wind project in the German Baltic Sea has been completed on schedule. The electric offshore transformer station has now been successfully installed at a water depth of almost 30 meters. Moving the so-called "topside" from a barge onto the foundation with the crane ship Oleg Strasnov was the installation of the world's heaviest alternating current platform, which had previously been lifted in one block on the high seas.

The largest single component of the billion-euro project weighs more than 5,000 tons and consists of the jacket foundation anchored in the seabed and the topside with the electrical switchgear and transformers. It is the size of an eight-storey apartment building and has a helipad at an altitude of 70 metres above sea level. The construction of the transformer station at the French shipyard STX required more than 500,000 working hours.

The joint venture consisting of E.ON and Statoil will jointly use the platform with the transmission grid operator 50Hertz. The unmanned station is located in the middle of the construction site of the wind farm and will bundle the electricity produced by the 60 wind turbines, which is then transported to the mainland by sea cable. The substation is operated from the operating station of the wind farm in the port of Mukran Port in Sassnitz on Rugen island, while E.ONs Offshore Marine Coordination Center in Hamburg monitors and controls the operation.

The next step in the construction phase will be the laying of the internal parking cabling. Finally, in late summer, the erection of the wind turbines on the foundations already installed will start. The complete commissioning of the entire wind farm is planned for 2019.

The Arkona project is located 35 kilometres northeast of the island of Rugen. The wind farm will have an output of 385 megawatts (MW) and can theoretically supply around 400,000 households with renewable energy. The investment volume amounts to 1.2 billion euros. Compared to conventionally generated electricity, Arkona saves up to 1.2 million tons of CO2 per year. 60 turbines in the six-megawatt class from Siemens will be installed. The plants are based on monopile foundations in water depths of 23 to 37 metres.

Source: E.ON

Similar Entries

Rostock-based company EEW Special Pipe Constructions GmbH has received an order from the Swedish energy group Vattenfall to produce 41 monopiles for the 344 MW offshore wind
farms Vesterhav. The contract was signed on 19 November 2021.

The first monopile for the Baltic Eagle offshore wind project is finished (pict. EEW SPC)

On 18 February 2022, the first monopile for the Baltic Eagle offshore wind farm was completed. The pile weighs 1,363 tonnes with a diameter of 9 metres. Baltic Eagle is already the second wind farm project of the Spanish energy company Iberdrola in the German Baltic Sea.

(l to r): Austin Coughlan, Head of Temporis Aurora Fund and Director of Inis Offshore Wind;  Vanessa O’Connell, Head of Inis Offshore Wind and Aoife Galvin, Senior Offshore Project Manager, Inis Offshore Wind, who joined from ESB (pict. ReputationInc)

Temporis Investment Management (“Temporis”) has on October 11th announced the launch of Inis Offshore Wind, a new Irish renewable energy firm with plans to develop at least 1GW of offshore wind capacity by 2030. This would constitute a significant contribution to Ireland’s offshore wind targets and provide enough electricity to power over 800,000 homes.

Norwind Offshore. from left:: Maren Kleven Fox, Magnus Kleven, Sverre Olav Farstad, Jon Ketil Gjørtz, Sverre Andreas Farstad, Svein Leon Aure, Espen Volstad, Eivind Volstad

Farstad, Volstad and Kleven are combining forces to establish the ship-owning company Norwind Offshore. The company will offer specialised vessels designed specifically for advanced maritime operations in the development and service of the offshore wind sector. Norwind Offshore has entered into a contract with Vard for the delivery of three vessels by 2024 - with options for two more vessels in 2025. The first vessel is due to be delivered in 2022.