First turbine successfully installed at Nordsee One

Thursday, 9 March, 2017 - 12:30
Installation of first Senvion turbine at Nordsee One was completed according to schedule. (Photo: innogy SE)
Installation of first Senvion turbine at Nordsee One was completed according to schedule. (Photo: innogy SE)

Installation of the 54 Senvion 6 MW wind turbines that will comprise the Nordsee One Offshore Wind Farm has commenced at the base port in Eemshaven.

Two sets of wind turbines each consisting of a fully assembly steel tower, a nacelle and a pre-assembled rotor, were loaded onto the installation vessel MPI Enterprise, which transported the components to the construction site at sea located approximately 40 km north off the island of Juist. Upon arrival at the offshore site, the first of the two turbines was installed using the installation vessel’s own crane.

The nacelles alone weigh-in at approx. 335 tonnes, the tower itself measures almost 70 metres overall in length, and weighs over 240 tonnes. Each rotor blade is 61 meters in length and weighs approximately 20 tonnes.

In April 2016 installation of the turbine foundations was completed. The substation was installed last summer, and the inter-array cable laying was successfully completed in September 2016. Once completed, the Nordsee One wind farm will consist of 54 wind turbines of the type Senvion 6.2M126 with an overall installed capacity of 332 MW. Commissioning of the wind farm is anticipated by the end of 2017. Nordsee One is owned by Northland Power Inc. (85%) and innogy SE (15%).

Pierre Lestienne, Managing Director (CFO) of Nordsee One GmbH explained: “We have reached this important milestone according to schedule and within budget. I'm really proud of this achievement. This outcome is the result of precise planning and efficient execution.”

Tim Kittelhake, Managing Director (COO) of Nordsee One GmbH added: “The team worked together hand-in-hand, so the loading of the first major components at our base port in Eemshaven, as well as the installation at sea, both went very smoothly. We look forward to installation of the next turbines, which will follow immediately. We plan to have all turbines installed and commissioned by the end of this year.”

Northland Power / innogy SE /
Nordsee One / Silke Funke

Similar Entries

MHI Vestas and Total formally announced their involvement in the Eolmed project this week (pict. Ideol)

MHIV and Total formally announced their involvement in the Eolmed project this week. These internationally recognized leaders and the project developer QAIR have agreed to combine their respective know-how’s and efforts to successfully develop and execute this 30MW pilot project.

Pin Piles for Greater Changhua OWF at Gwangyang Port (pict. EEW GROUP)

The EEW Group is pleased to announce that the production of 123 pin piles for the Greater Changhua 1 & 2a Offshore Wind Farms project has been successfully completed.

Edda Wind - Offshore Wind Service Vessels

Following the receipt of equipment orders for four offshore wind service vessels announced in May 2020, MacGregor, part of Cargotec, has received an additional order for another two Commissioning Service Operation Vessels (CSOV) that will further expand the Østensjø Rederi Edda Wind fleet.

On Friday September 4th, Siemens Gamesa, MHI Vestas, Blue Water Shipping, the Dockers Union, and Port Esbjerg came together to celebrate the joint approach to road safety within the Port of Esbjerg.

As a testament of the constant focus on safety in the offshore wind industry, neighbors at the Port of Esbjerg have teamed up to create a new safety initiative.

 
 
 

Contact