Foundations for Riffgat offshore wind farm in place

Tuesday, 11 September, 2012 - 14:45

All 30 foundations for the German Riffgat offshore wind farm, planned by EWE Energie AG in conjunction with Enova, have been installed. EWE announced in early September that work on the foundation structures had been completed on schedule. “I am very pleased that we have so successfully accomplished an important and challenging construction step,” EWE project manager Wilfried Hube said.

Inner-farm cabling and putting in the foundation for the transformer substation are next, as they need to be done before the substation’s topside and the turbines can be installed next year. The plan is to start the farm up in the summer of 2013.

Some 23,000 tons of steel have been used in Riffgat in the approximately 80 days of construction since driving the first piles in mid-June. A total of 200 people were busy at work out at sea in the last few weeks. Each foundation consists of a foundation pile up to 70 meters long and 750 tons heavy that was driven as much as 40 meters deep into the seabed. A transition piece is added to each one that will later connect the turbine tower to the foundation pile.

For the first time, a double-walled, tube-shaped soundproof barrier of steel was used when ramming the foundation pile. This was pulled over the foundation pile and had a sound-minimizing layer of air in the outer double tube and a multi-layered adjustable air bubble curtain in the inner tube that also reduces the sound. “The various measurements demonstrated that we came in below the 160-decibel level specified for the protection of marine animals during our pile driving,” reports Hube.

Katharina Garus

Similar Entries

The Heavy Lift Jack-Up Vessel Innovation lifted the Topside on the foundation (source: EnBW)

The Topside of the Offshore substation of the wind farm EnBW Albatros was installed the night from March 26 to 27, 2019. The Heavy Lift Jack-Up Vessel (HLJV) Pacific Ospray had loaded the Topside in Rotterdam.

Heerema marine contractors installing a monopile

Dutch offshore contractor Heerema has been assigned to help build the first and largest commercial offshore wind farm in the United States. The prestigious 'Vineyard Wind LLC' project is the nation's first utility-scale offshore wind energy project. Situated 14 miles off the coast of Massachusetts, this project will generate clean, renewable, cost-competitive energy for over 400,000 homes and businesses, while reducing carbon emissions by over 1.6 million tons per year.

Klaus Steen Mortensen, Chief Executive Officer of Bladt Industries (pict. Bladt)

Vineyard Wind LLC (Copenhagen Infrastructure Partners and Avangrid Renewables) and Bladt Industries have signed a contract for fabrication and delivery of the Vineyard Wind project’s offshore substation. The Vineyard Wind project will be first utility-scale offshore wind farm in the US. Bladt Industries is a global leader of substructures for offshore wind farms.

(Source: ResearchMoz Global Pvt. Ltd.)

The environmental regulatory pressure for reducing the emission of harmful substances from fossil fuel based energy resources is further expected to push the stake holders, either government or private entities, to opt for offshore wind energy sources, in their respective regions.

 
 

Contact