Internal park substation for DanTysk is ready

Tuesday, 23 July, 2013 - 11:00

After one and a half years of construction, the offshore substation for the wind farm DanTysk has been completed. The two transformers, all of the cables, the switchgear and utility rooms are installed. On 29 June, the substation rolled from the factory floor of the Hollandia shipyard in Rotterdam onto a transport crane, which will bring it to the construction site.

The substation will combine the power of all 80 turbines in the North Sea wind farm and bring it up to the required transport voltage of 155 kV. From this substation, the electricity makes its way to the cluster connection SylWin Alpha 10 km away.

During the loading process, the substation moved forward one centimetre at a time on a multi-wheeler, which is a kind of "centipede on wheels". It was approximately 100 m to the quay, where the barge that would transport it to the construction site waited for its freight, secured with thick mooring lines. Before loading began, the helicopter landing platform was also installed.


Photo Gallery


But how does one load a 3,000-tonne monster like that onto a transport barge, without it losing its balance in the water? The professionals at the Hollandia shipyard have the necessary experience. The transport barge has several air chambers which are partially filled with water. Normally, the weight of the substation would push the barge down during loading. However, the experts pump water out of the air chambers at exactly the right moment, so that the buoyancy force increases. The incoming tide helps to ensure that the loading area is at exactly the same height as the quay and the substation can be safely rolled up the ramp onto the boat.

Precision work - and the water level must be checked continuously. The loading process takes an entire day; finally, the substation is safely anchored in its brackets on the barge.

During the following days, the jacket-construction foundation was also loaded onto the barge, along with the piles for anchoring to the seabed.

Katharina Garus

Related article:

SylWin1 has been delayed

Similar Entries

The HLC successfully passed all tests (pict. Liebherr)

The HLC (Heavy Lift Crane) 295000 is on board the “Orion”, the next generation offshore installation vessel by DEME. Being the largest crane Liebherr has ever built, it has a maximum lifting capacity of 5,000 Tonnes. Its working field will be the offshore industry, in which it will help installing wind farms and decommissioning “old” energy platforms.

Medfloat Pilot Parc using SATH technology (pict. Saitec)

The Spanish engineering company Saitec has announced its interest in developing a pre-commercial pilot park with 5 units and a total potential of 50MW in the Mediterranean Sea in 2025. The offshore wind turbines will use SATH technology in open sea in Girona, specifically in an area located more 15 km from Cap de Creus on the Costa Brava (Catalonia)

The jacket, which will support the offshore platform substation, was secured on the seabed using the Saipem 7000 heavy lift vessel  (pict. SSE plc)

Construction of the world’s deepest fixed bottom offshore wind farm, which is also Scotland’s largest, has reached another milestone with the installation of a jacket in preparation for the project’s offshore substation topside which is due to be installed in early 2022.

Deployment of a patent protected 4T Filter Unit Rockbag on Saint Nazaire Offshore Wind Farm (pict. Ridgeway)

Saint-Nazaire Offshore Wind Farm will use Ridgeway Rockbags for cable stabilisation and protection.