Nearshore project Nordergründe put into operation

Wednesday, 20 December, 2017 - 14:45
wpd and the co-shareholders of the Nordergründe John Laing Group plc and the Gothaer Insurance Group announced that installation work has now been successfully completed. (Photo: wpd)
wpd and the co-shareholders of the Nordergründe John Laing Group plc and the Gothaer Insurance Group announced that installation work has now been successfully completed. (Photo: wpd)

The last of a total of 18 turbines of the 111 MW wind farm Nordergründe was connected to the grid  under the project management of the Bremen developer wpd.

Building work on the nearshore wind farm kicked off in May 2016: The first monopile for the Senvion turbines of the type 6.2M126 was set up 15 kilometres north-east of Wangerooge in the Weser estuary. All foundation structures had been completely installed in the mid of 2016. This was directly followed by installation of the wind turbines, which was completed at the beginning of December 2016.

The project faced with a serious challenge in September 2016 when the manufacturer of the offshore substation surprisingly filed for insolvency. A quick solution had to be found as to how further construction was to continue on the structure, which at that time consisted merely of a rough steel structure. “After analysing various possibilities, we decided together with banks and equity investors that completion of the construction should be managed by wpd alone“, explains Achim Berge Olsen, Managing Director of OWP Nordergründe GmbH & Co. KG and wpd offshore GmbH. In accordance with the revised programme, wpd completed installation of the substation at the end of September 2017. Since then work has involved successive commissioning of each individual turbine. “Yesterday was a special day for all of us. We are very happy to have successfully completed the project,” says Berge Olsen.

Nordergründe wind farm is located in water depths of up to ten metres within the 12-nautical mile zone of the German North Sea. Grid connection is facilitated by a single connection via the grid operator, Tennet. Manufacturers of the components for the wind farm originate from the German north-west region. In addition to Senvion (wind turbines) these include Ambau (foundations), NSW (internal wind farm cabling) and Bilfinger Marine & Offshore Systems, now Van Oord (installation). In future, Deutsche Windtechnik will assume operational management of the wind farm.

wpd / Funke

 

Similar Entries

Schaeffler and ZF use jointly developed expert models to analyze and predict the condition of wind turbine gearboxes based on the actual loads that occur during operation

ZF Friedrichshafen and Schaeffler are collaborating to develop new solutions for predicting the operating life of wind turbine gearbox components based on the actual loads that occur during operation. Since September, the first wind turbine gearboxes equipped with sensors and condition monitoring systems have been supplying operating data to a cloud-to-cloud solution to enable this to happen.

Heerema marine contractors installing a monopile

Dutch offshore contractor Heerema has been assigned to help build the first and largest commercial offshore wind farm in the United States. The prestigious 'Vineyard Wind LLC' project is the nation's first utility-scale offshore wind energy project. Situated 14 miles off the coast of Massachusetts, this project will generate clean, renewable, cost-competitive energy for over 400,000 homes and businesses, while reducing carbon emissions by over 1.6 million tons per year.

Sleipnir during LNG Bunkering (pict. Heerema Marine Contractors (HMC))

This week, Heerema’s newest vessel Sleipnir will begin her maiden voyage. Sleipnir, the world’s largest and strongest semi-submersible crane vessel (SSCV) was built in Singapore and will set course for Spain. The trip will take about 45 days.

The last three monopiles are loaded onto the barge in Rostock (pict.: EEW SPC/Van Oord)

On the evening of 19 December, 2018, EEW Special Pipe Constructions GmbH loaded the last three monopiles for the German offshore wind project Deutsche Bucht in the Rostock port.