Offshore transformer platform for DanTysk is complete

Monday, 12 August, 2013 - 10:45
Photo: Vattenfall

The most difficult crane lift in the German offshore wind project DanTysk is complete: On 1 August, the 3,200 tonne substation was positioned on its jacket substructure. The job was done by the crane vessel Oleg Strashnov, which also constructed both the foundation and the platform of the offshore transformer station in less than a week.

Seventy kilometres west of Sylt, around 200 people were involved in the effort of positioning the substation within a centimetre, which is 30 m high and has an area of 36 x 42 m."Assembling a 3,200-tonne colossus the size of a medium-sized office building in the middle of the North Sea in water 25 m deep isn't something you do every day. My compliments to the entire team, which did a fantastic job, despite weather conditions that were not quite optimal," said Holger Grubel, Project Manager at Vattenfall.

 


Photo Gallery


The transformer platform is scheduled to be technically operational by the end of September. Meanwhile, other tasks are also proceeding. About half of the steel foundations for the 80 wind turbines are already installed. In addition, a special ship is laying the cables that will connect the wind turbines to the substation. Currently, more than 450 people are employed and working on various tasks on more than ten ships at the sea construction site of DanTysk. Starting in mid-November, the wind turbines will be set up.

Later, when the wind farm is operational, the offshore transformer station will collect the wind power from all 80 turbines and ramp it up from an AC voltage of 30 kV to 155 kV and pass it to a converter station, from where the electricity will then be transmitted a distance of 165 km to shore as DC current.

DanTysk is scheduled to be operational in the fall of 2014. The offshore project is a joint venture by Vattenfall (51%) and Stadtwerke München (49 %). The investment costs amount to € 1 billion.

Katharina Garus
 

Related Articles:

Internal park substation for DanTysk is ready
SylWin1 has been delayed

Similar Entries

A.IKANBILIS is a unique hovering AUV designed and manufactured by BeeX in Singapore and provided to European customers by Subsea Europe Services (pict. Subsea Europe Services GmbH)

First trials at an operational wind farm demonstrate the transformative potential of true autonomy as subsea infrastructure project activity increases to meet green energy targets.

The jacket, which will support the offshore platform substation, was secured on the seabed using the Saipem 7000 heavy lift vessel  (pict. SSE plc)

Construction of the world’s deepest fixed bottom offshore wind farm, which is also Scotland’s largest, has reached another milestone with the installation of a jacket in preparation for the project’s offshore substation topside which is due to be installed in early 2022.

The first turbine jacket foundation is installed at the Seagreen Wind Farm site, 27 kilometres off the coast of the county of Angus in Scotland (pict: SSE Renewables)

The first turbine jacket foundation has been installed at Seagreen – Scotland’s largest and the world’s deepest, fixed bottom offshore wind farm.

(l to r): Austin Coughlan, Head of Temporis Aurora Fund and Director of Inis Offshore Wind;  Vanessa O’Connell, Head of Inis Offshore Wind and Aoife Galvin, Senior Offshore Project Manager, Inis Offshore Wind, who joined from ESB (pict. ReputationInc)

Temporis Investment Management (“Temporis”) has on October 11th announced the launch of Inis Offshore Wind, a new Irish renewable energy firm with plans to develop at least 1GW of offshore wind capacity by 2030. This would constitute a significant contribution to Ireland’s offshore wind targets and provide enough electricity to power over 800,000 homes.