Siemens Gamesa’s strong commercial performance in Q1 FY2020 reaffirms long-term prospects

Thursday, 6 February, 2020 - 11:30

Rising demand for wind power as a response to the transition towards non-polluting energies drove Siemens Gamesa's commercial activity in the first quarter of FY 2020. The company experienced an 82% increase in order intake, with firm orders rising to €4,628m, raising the order book to a record €28,089m, underlining solid long-term growth prospects.
As announced in a regulatory disclosure on 29 January, the company experienced an unforeseen €150m impact from costs on five onshore projects (1.1 GW) in northern Europe, mainly Norway, caused by adverse road conditions and the unusual early arrival of winter weather, which delayed project execution substantially. As a result, Siemens Gamesa adjusted its profitability target by one percentage point and expects to end the fiscal year with an EBIT margin before PPA, integration and restructuring costs of between 4.5% and 6%.
"This was not an easy quarter for Siemens Gamesa. The company's financial performance fell short of the expectations we had when we set our targets for the year. However, this was a one-off impact and we do not expect it to recur in future quarters as we are taking the necessary measures. We have stepped up risk analysis to ensure project execution is on track and we will also strengthen our internal control system to avoid a recurrence," said Markus Tacke, CEO of Siemens Gamesa.
"The results also underlined the long-term opportunities for wind energy and Siemens Gamesa. We are in an industry with huge potential and we are taking advantage of this with intense commercial activity that resulted in a record order book. Moreover, the acquisition of strategic assets from Senvion will boost our service business, where margins are higher," added Tacke.

Commercial activity increased significantly in the offshore segment, with order intake in the last twelve months doubling to 3,343 MW. Of that figure, 1,279 MW were signed in the first quarter. Siemens Gamesa is the clear leader in this segment, with a pipeline of projects totaling 9.6 GW2.
Onshore also registered very positive commercial activity, with order intake up 8.1% to 2.6 GW. China (18%) and Canada (16%) were the main sources of orders in the quarter. Moreover, almost half of orders were for the new models of turbines over 4 MW.
Service attained an extraordinary level of commercial activity, with order intake reaching €1,470m in Q1 FY2020, four times the figure in Q1 FY 2019. This business unit, which has very profitable contracts, accounts for 46% of the company's order book.

Between October and December, Siemens Gamesa booked €2,001m in revenue (-12%), in line with the full-year guidance (€10,200m-€10,600m). The low end of the revenue guidance has already been booked in orders.
The company remains focused on retaining a sound balance sheet. As of 31 December, it had a net cash position of €175m. Moreover, Siemens Gamesa has introduced sustainability criteria throughout its funding chain.

As evidenced by the order intake and backlog figures, demand for wind power is higher than ever. The GWEC estimates that global wind power installations will rise from 51 GW per year in 2018 to 130 GW per year in 2040.
Despite the current situation, Siemens Gamesa is solidly positioned to benefit from wind power's potential and to ensure success in the long term. It has scheduled a Capital Markets Day for 6 May, when it will give more details of the company's strategy for the coming years.

www.siemensgamesa.com

Quelle: 

Siemens Gamesa

Similar Entries

BSc (Hons) marine science students at the Scottish Association for Marine Science UHI, Dunstaffnage

The ScotWind partnership involving leading renewable energy developer SSE Renewables, Japanese conglomerate Marubeni Corporation (Marubeni) and Danish fund management company Copenhagen Infrastructure Partners (CIP) have signed a memorandum of understanding (MOU) with the University of Highlands and Islands for a collaboration to deliver targeted education, research and employability initiatives

(l to r): Austin Coughlan, Head of Temporis Aurora Fund and Director of Inis Offshore Wind;  Vanessa O’Connell, Head of Inis Offshore Wind and Aoife Galvin, Senior Offshore Project Manager, Inis Offshore Wind, who joined from ESB (pict. ReputationInc)

Temporis Investment Management (“Temporis”) has on October 11th announced the launch of Inis Offshore Wind, a new Irish renewable energy firm with plans to develop at least 1GW of offshore wind capacity by 2030. This would constitute a significant contribution to Ireland’s offshore wind targets and provide enough electricity to power over 800,000 homes.

Working closely with platform manufacturer Aibel, Dogger Bank Wind Farm will use an unmanned HVDC substation design – a world-first, slashing weight and cost. Upon first installation in Dogger Bank A during 2023, the project’s HVDC facility will also become the largest-ever at 1.2GW, marking a tremendous scale up from the previous industry benchmark of 0.8GW (pict.: Aibel)

Dogger Bank Wind Farm is breaking yet more records as the project announces a revolutionary platform design, unveiling the world’s first unmanned High Voltage Direct Current (HVDC) offshore substation.

Norwind Offshore. from left:: Maren Kleven Fox, Magnus Kleven, Sverre Olav Farstad, Jon Ketil Gjørtz, Sverre Andreas Farstad, Svein Leon Aure, Espen Volstad, Eivind Volstad

Farstad, Volstad and Kleven are combining forces to establish the ship-owning company Norwind Offshore. The company will offer specialised vessels designed specifically for advanced maritime operations in the development and service of the offshore wind sector. Norwind Offshore has entered into a contract with Vard for the delivery of three vessels by 2024 - with options for two more vessels in 2025. The first vessel is due to be delivered in 2022.