First Monopiles for Hornsea Project 1 have left EEW SPC

Sunday, 21 January, 2018 - 16:00

The first six monopiles for the Ørsted project Hornsea Project 1 were loaded at the quay in Rostock from 18th to 21st December 2017. With the crane vessel „SVENJA“ from the company SAL Heavylift the foundations, which are all about 65 m long and weigh 800 tonnes each, will now be on the way to Able Seaton Port in Great Britain, where they will be temporarily stored until installation commences.

The production at EEW SPC is exactly on schedule. The first 48 monopiles have to be shipped by the end of January 2018. EEW SPC will be ready for load out three weeks earlier.

In total EEW SPC will produce 174 monopile foundations, with each having a diameter of 8.1 metres. The largest offshore wind project to date is intended to deliver electricity for well over one million households from 2020.

Source: EEW SPC

Similar Entries

Hornsea Project Two is the largest offshore project in Siemens Gamesa's history to date. (Photo: Siemens Gamesa)

Siemens Gamesa has been awarded a contract for the delivery and service of turbines with a combinded capayity of 1,386 MW. The project is being developed by the Danish energy group Ørsted in British waters.

International marine and engineering consultancy LOC Renewables is carrying out marine warranty surveying (MWS) services on what will be the world’s biggest wind farm, DONG Energy’s Hornsea Project One. The site, which will consist of 174 turbines installed off the Yorkshire coast in the North Sea and deliver power to more than one million homes, is scheduled for commissioning in 2020.

In response to media speculation, Ørsted confirms that it is in exclusive discussions regarding a 50% farm-down of the offshore wind farm Hornsea 1.

8.2 Consulting AG is proud to be part of the pan-European consortium that participates in the Horizon 2020 project - a technology platform for the first prototype of a double-digit rated capacity turbine in a realistic offshore environment.