German wind farm Hohe See is on its way

Tuesday, 21 February, 2017 - 14:30
At EnBW Hohe See Siemens will install 71 units of its turbine type SWT-7.0-154, rated at 7 MW and with a rotor diameter of 154 m. (Photo: Siemens)
At EnBW Hohe See Siemens will install 71 units of its turbine type SWT-7.0-154, rated at 7 MW and with a rotor diameter of 154 m. (Photo: Siemens)

Siemens will provide the complete offshore wind power plant solutions for the Hohe See offshore wind project 90 km north of the German island Borkum. The inter-array cabling contract with a value of approximately € 80 million has been awarded to VBMS.

The Hohe See offshore wind project is the largest German offshore wind farm to date. It will stretch over an area of 40 km². The 71 wind turbines to be installed at the site will have a combined capacity of just less than half a Gigawatt. 50,1 % of the park is owned by the EnBW The other 49,9% are owned by Enbridge Inc. Both companies agreed on joining forces during the construction of the project and afterwards.

Siemens started to develop the project-specific solution for the foundations of the wind power plant last year. As a result they came up with a monopile design with a length of up to 80 m and a weight of up to 1,500 t to anchor the wind turbines solidly into the sea bed at a water depths of up to 40 m. These foundations as well as the transitions pieces will be delivered by Siemens’ partner GeoSea.

VBMS, a subsidiary of Boskalis will provide the inter-array cabling. The works include the supply, installation and burial as well as termination and testing of 79 33-kV-inter-array cables.

After the final investment decision at the end of 2016, the construction works are going to start in early 2018 and are expected to be finished in the third quarter of 2019.

Philipp Kronsbein

Similar Entries

In order to determine whether the offshore wind farm Albatros in the North Sea is economically and technically feasible, EnBW Energie Baden-Württemberg AG has initiated the tendering process for the combined lot 'wind energy plant, foundations and offshore substation' and for the lot 'cable work within the wind farm'.

Nordergründe is one of several projects that are currently under construction and are still covered by the old EEG. (Photo: Torsten Thomas)

Despite all of the cuts, the European offshore wind market is still large. Nevertheless, players on the German market are preparing for lean times. The 730 MW per year that policymakers have committed to are a very modest goal.

Meerwind has a total capacity of 288 MW and was one of the largest German offshore wind farms to achieve full financial closing. (Photo: WindMW GmbH)

The US-American Blackstone Group has entered a definitive agreement to sell its majority interest in WindMW GmbH, the owner of one of Germany’s largest offshore wind farms Meerwind. Buyer is China Three Gorges Corporation, a Chinese state-owned and globally operating power company.

All 54 monopiles for the Nordsee One offshore wind farm were successfully built six weeks ahead of schedule.  (Photo: RWE)

The last foundation for the Nordsee One offshore wind farm is completed and all 54 monopole foundations have been fitted with the associated transition pieces for the installation of the tower segments.