German wind farm Hohe See is on its way

Tuesday, 21 February, 2017 - 14:30
At EnBW Hohe See Siemens will install 71 units of its turbine type SWT-7.0-154, rated at 7 MW and with a rotor diameter of 154 m. (Photo: Siemens)
At EnBW Hohe See Siemens will install 71 units of its turbine type SWT-7.0-154, rated at 7 MW and with a rotor diameter of 154 m. (Photo: Siemens)

Siemens will provide the complete offshore wind power plant solutions for the Hohe See offshore wind project 90 km north of the German island Borkum. The inter-array cabling contract with a value of approximately € 80 million has been awarded to VBMS.

The Hohe See offshore wind project is the largest German offshore wind farm to date. It will stretch over an area of 40 km². The 71 wind turbines to be installed at the site will have a combined capacity of just less than half a Gigawatt. 50,1 % of the park is owned by the EnBW The other 49,9% are owned by Enbridge Inc. Both companies agreed on joining forces during the construction of the project and afterwards.

Siemens started to develop the project-specific solution for the foundations of the wind power plant last year. As a result they came up with a monopile design with a length of up to 80 m and a weight of up to 1,500 t to anchor the wind turbines solidly into the sea bed at a water depths of up to 40 m. These foundations as well as the transitions pieces will be delivered by Siemens’ partner GeoSea.

VBMS, a subsidiary of Boskalis will provide the inter-array cabling. The works include the supply, installation and burial as well as termination and testing of 79 33-kV-inter-array cables.

After the final investment decision at the end of 2016, the construction works are going to start in early 2018 and are expected to be finished in the third quarter of 2019.

Philipp Kronsbein

Similar Entries

Full-scope-project EnBW Albatros: Siemens Gamesa supplies 16 direct-drive SWT-7.0-154 wind turbines on monopile foundations and the grid connection via a Siemens Offshore Transformer Module. (Photo: Siemens Gamesa)

Following the 497 MW order for the EnBW Hohe See offshore wind farm, EnBW has also awarded Siemens Gamesa Renewable Energy with the installation of the neighbouring 112 MW project EnBW Albatros.

EnBW Energie Baden-Württemberg AG has increased the pace at which it is expanding wind energy at sea: Just a few days after having its bid for the 900 megawatt project EnBW He Dreiht accepted in Germany's first offshore wind power auction, the company's Supervisory Board has now given the green light for the next offshore wind farm EnBW Albatros and approved the final decisions taken regarding construction and investment.

DEME Group’s offshore marine engineering subsidiary GeoSea announces today that, following successful completion of the design, it also received the Notice to Proceed for fabrication and offshore installation of 16 wind turbine foundations and 1 Offshore Transformer Module (OTM) for the EnBW Albatros offshore wind farm, for which GeoSea is Siemens’ EPCI partner. This partnership enables Siemens to provide a full-scope project (offshore wind turbines and OTM, incl. foundations) to EnBW.

TÜV SÜD presented the project certificate for the Sandbank offshore wind farm off the coast of Sylt in the North Sea. (Photo: Vattenfall)

TÜV SÜD’s experts have supported the large-scale project over the past 30 months. Certification was awarded in accordance with the standard of the German Maritime and Hydrographic Agency (BSH), and covers supervision and inspection of wind turbine, foundation, sub-station and internal cable manufacturing, transport, installation and commissioning for the wind farm.