Nearshore project Nordergründe put into operation

Wednesday, 20 December, 2017 - 14:45
wpd and the co-shareholders of the Nordergründe John Laing Group plc and the Gothaer Insurance Group announced that installation work has now been successfully completed. (Photo: wpd)
wpd and the co-shareholders of the Nordergründe John Laing Group plc and the Gothaer Insurance Group announced that installation work has now been successfully completed. (Photo: wpd)

The last of a total of 18 turbines of the 111 MW wind farm Nordergründe was connected to the grid  under the project management of the Bremen developer wpd.

Building work on the nearshore wind farm kicked off in May 2016: The first monopile for the Senvion turbines of the type 6.2M126 was set up 15 kilometres north-east of Wangerooge in the Weser estuary. All foundation structures had been completely installed in the mid of 2016. This was directly followed by installation of the wind turbines, which was completed at the beginning of December 2016.

The project faced with a serious challenge in September 2016 when the manufacturer of the offshore substation surprisingly filed for insolvency. A quick solution had to be found as to how further construction was to continue on the structure, which at that time consisted merely of a rough steel structure. “After analysing various possibilities, we decided together with banks and equity investors that completion of the construction should be managed by wpd alone“, explains Achim Berge Olsen, Managing Director of OWP Nordergründe GmbH & Co. KG and wpd offshore GmbH. In accordance with the revised programme, wpd completed installation of the substation at the end of September 2017. Since then work has involved successive commissioning of each individual turbine. “Yesterday was a special day for all of us. We are very happy to have successfully completed the project,” says Berge Olsen.

Nordergründe wind farm is located in water depths of up to ten metres within the 12-nautical mile zone of the German North Sea. Grid connection is facilitated by a single connection via the grid operator, Tennet. Manufacturers of the components for the wind farm originate from the German north-west region. In addition to Senvion (wind turbines) these include Ambau (foundations), NSW (internal wind farm cabling) and Bilfinger Marine & Offshore Systems, now Van Oord (installation). In future, Deutsche Windtechnik will assume operational management of the wind farm.

wpd / Funke

 

Similar Entries

Schaeffler and ZF use jointly developed expert models to analyze and predict the condition of wind turbine gearboxes based on the actual loads that occur during operation

ZF Friedrichshafen and Schaeffler are collaborating to develop new solutions for predicting the operating life of wind turbine gearbox components based on the actual loads that occur during operation.

The heart of the Arkona offshore wind project in the German Baltic Sea has been completed on schedule. The electric offshore transformer station has now been successfully installed at a water depth of almost 30 meters. Moving the so-called "topside" from a barge onto the foundation with the crane ship Oleg Strasnov was the installation of the world's heaviest alternating current platform, which had previously been lifted in one block on the high seas.

Hornsea Project Two is the largest offshore project in Siemens Gamesa's history to date. (Photo: Siemens Gamesa)

Siemens Gamesa has been awarded a contract for the delivery and service of turbines with a combinded capayity of 1,386 MW. The project is being developed by the Danish energy group Ørsted in British waters.

In 2017, Mammoet, heavy lifting and transport specialist, has been contracted by Lamprell Energy for the heavy lifting and transport of 60 jacket foundations for the East Anglia One offshore wind farm project.